Owner: Valley Metro Rail
Location: Tempe and Mesa, AZ
Status: Under Construction
Construction Period: July 2005 to March 2008
Contract Amount: $71.9 million
Alignment Description: Line Section 5 consists of the construction of LRT guideway of approximately 4.9 route miles, from First Street in downtown Tempe thru Arizona State University to Sycamore in Mesa.

Unique Features:

  · 2 existing bridges demolished and reconstructed
  · 48,000 SF of cast in place retaining walls
  · ASU Promenade construction with 40,000 SF
    of sand set pavers
  · 25,000 LF of storm drain
  · 8 passenger station foundations
  · 4 embedded turnouts and 8 embedded crossovers
  · Projected final DBE utilization = 21%
  · 100% approval rating from the community for
    business/impact mitigation
  · Provided assistance with significant
    archaeological discoveries

To all involved in the closure of Mill Avenue for the track work, a BIG thanks to you all for your efforts in meeting the deadline. I appreciate your dedication to the project and as always, making my job a whole lot easier!
- E-mail received from Jyme Sue McLaren, Light Rail Project Manager, City of Tempe