Owner: San Francisco MUNI
Location: San Francisco, CA
Status: Construction Completed
Construction Period: Aug. 1997 to May 1999
Contract Amount: $14 million

Unique Features:

  · Utility and Roadway Reconstruction
  · New “Paved Track” Construction
  · 10 Million Visitors / Year
  · First Usage of “Storefront” Barricades
  · Weekly Merchant Meetings during Construction
  · Completed 8 Months Early



"The Fisherman’s Wharf area with over 10 million visitors last year would pose challenges for any construction contract, let alone one with street reconstruction and streetcar track construction work. If someone told me a year ago that all track construction, street reconstruction and traffic signal work for the project would be completed in less than 10 months, I would have thought that person was hallucinating. But the results speak of your achievement. Needless to say, the Wharf community is delighted with the accomplishment, especially since the project endured one of the wettest rainy
seasons in history"

- Don Chee Senior Project Manager, San Francisco MUNI
July 7, 1998

"In the beginning we had our fears, but we overcame those fears when your company joined in a team effort with the business community to make sure work would be done with minimal disruption. Stacy and Witbeck demonstrated creativity as they worked while keeping traffic flowing, assuring economic vitality in San Francisco’s most popular tourist destination with over 12 million visitors a year."

"Thanks to company vision, your crews became “Ambassadors of Goodwill” for the Fisherman’s Wharf, and the project itself, became a tourist attraction. … When the historic F-Line trolley is in service, the business community of Fisherman’s Wharf will always remember the outstanding contribution Stacy and Witbeck made to the preservation and betterment of the area and its historic tradition. A job well done!"

- Alessandro Baccari, Executive Secretary, Fisherman’s Wharf Association
December 1, 1998