Stacy Witbeck https://www.stacywitbeck.com/Areas/CMS/assets/img/STW-logo.png California CSLB #414305,2800 Harbor Bay Parkway
Alameda, CA 94502
510.748.1870

About the Project

This $73 million bid-build contract included furnishing, installing, and testing more than eight miles of direct fixation trackwork and related elements for two parallel tunnels and an elevated guideway. This included fabricating and installing over 7,000 feet of non-magnetic heavy-weight floating track slabs with ultra-straight rail to mitigate vibration impacts to the University of Washington’s science labs above.

This project marks the first project in the US to make thermite and flash butt welds to European high-speed rail standards. 

Project Awards:

John L. Martin Partnered Project of the Year Award - International Partnering Institute

AGC of Washington - Highway Transportation Over $50M. 

Quick Facts

Location

Seattle, WA

Project Type

Specialty Rail

Delivery Method

Bid-Build

Date Completed

2019

Project Owner

Sound Transit

Region

Northwest

/